Invalid payment claims and notices under construction contracts

Alert
|
8 min read

A key part of the interim payment process in construction projects is the issuing of payment notices by payee and payer alike. Two recent UK cases demonstrate a strict approach being taken by the courts to the validity of payment notices.

 

Introduction

In the UK, the use of payment notices in relation to construction contracts is mandated by the Housing Grants, Construction and Regeneration Act 1996 (as amended) (the "Act"), which applies to construction contracts involving works performed within (but not outside) the UK. The Act operates so that a payer (e.g. an employer) is obliged to pay the full amount set out in a valid payment notice issued by a payee (e.g. a contractor) if the payer fails to serve a valid "pay less" notice in time. This may be the case even if the payee is not entitled under the contract to the full amount which it claims for the relevant work performed. 

Similar legislation operates in a number of countries, including Singapore, Australia, New Zealand, Malaysia and Canada. The broad purpose of this legislation is to assist the cash flow of businesses that carry out construction work. The scheme of the legislation requires each party to a contract to issue payment claims and notices to each other, at particular times and giving particular details. If a notice is not issued validly, in accordance with the legislation, particular monetary consequences may follow.

The UK legislation lacks detail on the requirements for payment claims and notices under the Act, and when they will (and will not) be valid. Guidance from the courts on the application of these provisions is therefore welcome. Two recent cases shed light on how payment notice requirements will be interpreted.

 

Case 1: Downs Road Development LLP v Laxmanbhai Construction (U.K.) Ltd [2021] EWHC 2441 (TCC) 

This case concerned a dispute between Downs Road, the Employer, and Laxmanbhai, the Contractor, relating to the construction of residential units and associated works in London. 

  • The contract was an amended form of the 2011 JCT Design and Build Contract. In line with section 110A(1) of the Act, the contract required that the Employer provide a payment notice to the Contractor no later than five days after the payment due date. 
  • The Employer, however, took an unconventional approach to the issuing of payment notices. For each payment cycle, it issued two payment notices. The first (issued no later than five days after each payment due date) was equivalent to a "holding notice", specifying a nominal amount due of around £1. The second, issued some days later, and out of time, would contain a higher valuation.
  • One of the questions for the court was the validity of the notices and whether they conformed to the statutory requirement (reflected in the contract) that each payment notice "shall specify the sum that the party giving the notice considers to be or have been due at the due date in respect of the relevant payment and the basis on which that sum has been calculated".
  • As the Employer accepted that the second payment notice was out of time and accordingly invalid, the court was only asked to determine if the first notice was valid. 

The court decided that the first notice was invalid because the sum stated as due (i.e. around £1) was not one that the Employer "genuinely considered" to be due, i.e. it was simply a nominal or holding amount. The covering email that accompanied the payment notice supported this conclusion, as did the fact that this was a practice that the Employer had repeatedly adopted in previous payment cycles. Furthermore, the Employer's payment notice failed to set out the basis of the Employer’s calculation, as it did not include any supporting material or an explanation as to how the Employer had arrived at its gross valuation.

 

Case 2: D McLaughlin & Sons Ltd v East Ayrshire Council [2021] CSOH 122

This case concerned a dispute between the Contractor, D McLaughlin & Sons Ltd, and the Employer, East Ayrshire Council, relating to the construction of a school extension. 

  • The contract was an amended Standard Building Contract with Quantities for use in Scotland (SBC/Q/Scot) 2011. It provided (consistently with the requirements of the Act) that the Contractor may issue an Interim Payment Notice "stating the sum that the Contractor considers to be or to have been due to him at the relevant due date in accordance with clause 4.9.2 and the basis on which that sum has been calculated". 
  • One of the issues in dispute was how the validity of an Interim Payment Notice might be affected by the specification in the notice of an incorrect due date.
  • The parties were in agreement that the relevant due date should be four weeks after the works commenced, and thereafter the same date each following month. 
  • However, the parties disagreed on the date when the works commenced. As a result of this disagreement, the Contractor's notice specified a relevant due date that was one day earlier than what the Employer contended it should be. 

The court did not have to decide when the works commenced, because the Council's claim was barred on other grounds. However, the court rejected the Contractor's argument that the notice would be valid regardless of whether the Contractor or Employer was correct as to the due date. As the service of an Interim Payment Notice by the Contractor places the Employer at risk that a failure to serve a Pay Less Notice at the correct time may render it liable for the amount claimed, the Contractor must ensure proper notice is given. The court reasoned that if the Contractor specifies an incorrect due date in its payment notice, this does not meet the requirements of the Contract or the Act, and therefore the Contractor's payment notice is invalid.

 

Commercial Implications

These two cases provide helpful guidance for parties to construction contracts on the content and timing requirements of payment notices.

First, it has been clarified that a requirement to specify the sum that a payer "considers" due requires the payer to genuinely consider the sum to be due. Given the difficulty in determining a party's subjective intent, the courts will assess the genuineness of a party's valuation by reference to objective facts that indicate whether a sum stated to be due is actually what the payer "considers" is due. In Downs Road, this was clearly not the position at all, as the Employer issued two different payment notices for different amounts, and the first notice (for around £1) could not rationally be viewed as a sum which the Employer "considered" was due.

Aside from the (extreme) circumstances in Downs Road, there are other situations in which an Employer's payment notice may be open to attack for not specifying the sum the Employer genuinely considers to be due. For example, where an Employer deliberately refuses to value, or deliberately devalues, items of work claimed by a Contractor as part of a commercial or negotiation strategy to force the Contractor into an unfavourable position for the purposes of settling the final account. 

What, therefore, the Act and corresponding contractual provisions require is a bona fide assessment of a Contractor's payment claim. There is a similar requirement under forms of contract used internationally, e.g. the FIDIC Red and Yellow Books (1999 and 2017) require the Engineer to issue Interim Payment Certificates stating the amount that the Engineer "fairly determines to be due" to the Contractor. A failure by the Engineer to do so may have serious consequences for the Employer, including even the termination of the contract by the Contractor.

Secondly, where Contractors' payment claims are concerned, the failure to specify the correct due date in the payment notice may invalidate the notice. The Act requires Contractors' (and Employers') notices to specify the amount the Contractor "considers to be due or to have been due at the payment due date". If, therefore, a Contractor's payment claim states that it considers the sum of £X to be due as at date Y, when date Z was the true due date, the notice does not fulfil the requirements of the Act (and any contract that implements these requirements).

In many contracts it is made clear what the payment due date is (e.g. "the 28th day of each calendar month"), so there is no ambiguity. But if it is unclear, one possible solution is for Contractor and Employer to agree on what this date should be. Failing that, it may be sufficient to state that the notice is issued in respect of the due date of a particular application cycle, rather than specifying an actual date in the notice, provided it is otherwise clear and unambiguous that the payment notice relates to a specific due date. Such an approach was endorsed in the English case of Henia Investments Inc v Beck Interiors Ltd [2015] EWHC 2433 (TCC). 

Above all, these cases reinforce the notion that at the outset of each project, employers, contractors and engineers alike need to set in place systems and procedures for making and processing interim payment applications in accordance with the contract and any applicable legislation.

 

White & Case means the international legal practice comprising White & Case LLP, a New York State registered limited liability partnership, White & Case LLP, a limited liability partnership incorporated under English law and all other affiliated partnerships, companies and entities.

This article is prepared for the general information of interested persons. It is not, and does not attempt to be, comprehensive in nature. Due to the general nature of its content, it should not be regarded as legal advice.

© 2022 White & Case LLP

 

Top